Permit Approval

 

Average Permit Approval Time From Date of Completed Routine Application
Air Permit Varies: 6-9 Months
Water Permit Varies; Plumbing permit must be obtained and fee paid first
Plumbing Permit 1 hr at most (for licensed plumber)
Hazardous Waste Permit 18 Months
Industrial Wastewater Permit Varies; 1-3 weeks