As you visit this site you will find pieces of information that you may want to add to a Custom Profile. To do that simply click the "add" link that is associated with that information. Once you are finished gathering data simply click "View Custom Report" and that will take you directly to your report. From there you can email, print or create a PDF of that report.

Average Permit Approval Time From Date of Completed Routine Application
Air Permit Varies: 6-9 Months
Water Permit Varies; Plumbing permit must be obtained and fee paid first
Plumbing Permit 1 hr at most (for licensed plumber)
Hazardous Waste Permit 18 Months
Industrial Wastewater Permit Varies; 1-3 weeks